Template-Type: ReDIF-Article 1.0 Author-Name: David Newbery Title: The Cost of Finance and the Cost of Carbon: A Case Study of Britain's only PWR Classification-JEL: F0 Volume: Volume 10 Issue: Number 2 Year: 2021 Abstract: This paper argues that the cost of decarbonising depends critically on the Weighted Average Cost of Capital (WACC), illustrated with a case study of Sizewell B (SZB, the nuclear station commissioned in 1995). It calculates the cost per tonne of CO2 abated with prices set as for transmission assets by the regulator under the Regulatory Asset Base model. The cost depends critically on the WACC set in comparable utility price controls. At a low WACC the cost is £201936.2/tonne CO2 abated and £201943.3/t. CO2 at the high WACC, compared with the roughly £40/t. CO2 paid by GB generators in 2019. Moving from the social discount rate of 2.5% to a hurdle rate of 8% increases the cost from £1520/t. to over £60/t. Had Britain continued building replicas of SZB the cost saving compared to the current programme might be £2019919 billion. Handle: RePEc:aen:eeepjl:eeep10-2-Newbery File-URL: http://www.iaee.org/en/publications/eeeparticle.aspx?id=388 File-Format: text/html File-Restriction: Access to full text is restricted to IAEE members and subscribers.